US · APLD · 追跡

Applied Digital Corp.の継続追跡

The long-term argument is unchanged…

更新日

The long-term argument is unchanged and still supported by the company's own disclosure: Applied Digital has converted itself from a Bitcoin mining host into a landlord of AI compute, with contracted…

追跡の論理

  • Delivery is repeatable, with campuses coming online on schedule · Stronger —— Live critical IT load reached 275 MW by November 24, 2026 as the second campus delivered its first Ready for Service…
  • Record lease pricing shows powered AI capacity is scarce · Holding
  • Stabilised rent economics are proven at an 89% margin · Holding
  • Project financing, not demand, decides the outcome of the contracted book · Holding —— Three of five campuses still lack permanent project financing, with closings guided only to the first half of…
  • Dilution and senior claims sit ahead of the common equity · Weaker

重要な出来事

  • 2026-11-25 Lease pop fully fades, shares close at $12.29 near a 52-week low as targets are cut —— After a 20% to 26% jump on the November 23 lease, the shares fell 11.6% on November 24 and closed at $12.29 on November 25 with a 52-week low of $10.78, while p
  • 2026-11-24 Form 8-K raises the convertible preferred commitment to $2.5 billion from $2.0 billion —— The letter agreement with Series G preferred investors increased the equity commitment by $500 million, leaving $1.035 billion undrawn, showing the equity backs
  • 2026-11-24 First 25 MW Ready for Service at Polaris Forge 2 in Harwood, North Dakota —— The company completed base-build commissioning of the first 75 MW of its initial 150 MW Polaris Forge 2 building and brought the first 25 MW data hall to Ready
  • 2026-11-20 Shares fall 17.8% to $11.49 with no company announcement or filing —— Applied Digital fell 17.8% on November 20, 2026 while the S&P 500 lost 3.7%, in a sector-wide AI infrastructure sell-off with no company-specific news, showing

主な予定

  • 2026-12-31 Year-end target of about 300 MW of critical IT load live across North Dakota
  • 2026-12-31 Expected signing of about 250 MW of expansion leases at rates more than 15% above prior contracts
  • 2027-01-06 Fiscal Q2 2027 results (quarter ended November 30, 2026)
  • 2027-01-31 Expected project financing closings for Delta Forge 1 and Polaris Forge 3