← Back to Applied Digital Corp.
Company Research · APLD

Applied Digital Corp. research: A $41 billion lease book that still has to be financed

Applied Digital Corp. research: A $41 billion lease book that still has to be financed. The contract book is real and repricing upward, but the equity is a fin…

Applied Digital Corp.Published 2026-11-26Updated 2026-11-26Preview

See ongoing tracking and what changed for Applied Digital Corp.

Financial reporting period: fiscal first quarter ended August 31, 2026 (fiscal year ends May 31)

Core judgment

Applied Digital has converted itself from a Bitcoin mining host into a landlord for artificial intelligence computing. It now holds more than $41 billion of contracted base-term lease revenue across more than 1.6 gigawatts of critical IT load, and on November 23, 2026 it signed a further 18-year lease at better pricing than its earlier deals.〔source〕 The contracts are real, take-or-pay, and mostly signed with investment-grade tenants. What is not yet settled is who pays for the buildings that generate that rent.

First, rent has started to arrive, and the campuses that are running earn a very high margin on the rent line.

Base rent from AI tenants was $65.8 million in the quarter. Net operating income, meaning rent left after the running costs of the property such as power, insurance and local taxes, was $58.8 million, an 89% margin. The AI campus segment moved from a $2.0 million operating loss a year earlier to a $33.4 million operating profit.〔source〕

Second, most of the headline revenue is construction work, not rent.

Of $341.9 million of revenue in the quarter, $183.5 million was tenant fit-out services: the electrical and cooling build-out inside halls the tenants then fill with their own processors. Base rent was $65.8 million, and $13.3 million of "recoveries" was operating cost passed back to tenants with no margin attached.〔source〕

Third, the equity is a financing option, and the market is pricing it as one.

The company spent $2.1 billion on construction in the quarter, against about $250 million a year earlier. It covered that with $1.5 billion of new borrowing, preferred stock and revolver draws, so its cash balance was preserved rather than consumed.

The bill is now visible. Interest of $77.4 million in the quarter is larger than the $46.8 million the two operating businesses earned, and three of the five campuses still had no permanent project financing in November 2026: Delta Forge 1, Polaris Forge 3 and Delta Forge 2.〔source〕〔source〕

What this means for value. At the November 25, 2026 close of $12.29, the market is paying for roughly 400 megawatts of capacity already paying rent and close to nothing for the remaining 1.2 gigawatts of signed leases. My base case, in which about two-thirds of the contracted capacity that is not yet built is built and financed on roughly current terms, is about $28 per share. The bear case is about $6, roughly half the current price. The single question that decides which one happens is narrow and observable: whether Delta Forge 1, Polaris Forge 3 and Delta Forge 2 can be financed in the first half of calendar 2027.

What the company does and who pays

Applied Digital designs, builds, owns and operates large "AI factory" campuses: buildings with power, liquid cooling and fibre that house thousands of graphics processors for tenants that supply their own equipment.〔source〕

The tenant pays a fixed annual rent under a long, take-or-pay lease. If the tenant switches its machines off, it still owes the rent. Each lease begins only when a building reaches ready for service, so revenue follows construction rather than the contract signature.

In a typical scenario, a hyperscaler wants 150 megawatts of powered, liquid-cooled capacity delivered in North Dakota in 2028. Applied Digital builds the campus, arranges the power, finances most of the cost with project debt and outside equity, and collects rent for 15 to 18 years. Renewal options can extend the relationship to 33 years.

Wide aerial rendering of a completed data-center complex with white industrial buildings, rooftop eq Figure: A rendering of a large completed AI data-center campus and its supporting infrastructure.; source: new.abb.com.

The company also runs two smaller businesses. Its data center hosting segment rents powered space to one Bitcoin miner across two North Dakota sites. It produced $37.8 million of revenue and $13.3 million of segment operating profit in the quarter, on a contract with roughly a year and a half left that the tenant can cut.〔source〕

ChronoScale, a separately listed accelerated-computing company about 96% owned by Applied Digital, sells GPU compute. It added $41.5 million of revenue, including $23.0 million of GPU hardware sales. Management expects ChronoScale to reach $1 billion of annual recurring revenue in 2027, which is a company expectation rather than a reported result.〔source〕

How the money is actually earned today

The revenue line looks spectacular and the rent line is small. That gap is the single most important qualification on this company.

{"title": "Applied Digital revenue by source, Q1 fiscal 2027 (USD M)", "url": "https://aistockvalue.com/api/v1/stockmind/report-assets/b90f210c-28b4-4406-b257-a10c5981e135/134e8a66f768b21f/widget-134e8a66f768b21f.html"}

Three tenants pay nearly all of the revenue. The newest lease, signed on November 23, 2026, covers 150 megawatts for 18 years and about $5.4 billion of base-term revenue, with about $12.7 billion if every renewal option is exercised. It carries improved terms including higher pricing than earlier leases, and delivery is expected from the first half of calendar 2028.〔source〕

After it, total contracted base-term revenue exceeds $41 billion, the portfolio is over 1.6 gigawatts of contracted critical IT load, and roughly 75% of base-term revenue comes from investment-grade tenants.〔source〕

The leases themselves give the price, and this is the calculation the whole valuation rests on. Applied Digital's own table of signed leases divides as follows.

Lease Capacity Contracted revenue Term Implied annual rent per MW (USD M)
Polaris Forge 1 (CoreWeave) 400 MW ~$11.0B 15 years 1.83
Polaris Forge 2 200 MW ~$5.0B 15 years 1.67
Polaris Forge 3 300 MW ~$7.5B 15 years 1.67
Delta Forge 2 210 MW ~$5.2B 15 years 1.65
New lease, Nov 2026 150 MW ~$5.4B 18 years 2.00

Delta Forge 1, 300 MW under two leases, is not shown because its contracted revenue has not been disclosed separately. Including it, the signed portfolio is over 1.6 gigawatts.

So existing leases run at $1.65 million to $1.83 million of rent per megawatt per year, and the newest one is priced above all of them.〔source〕〔source〕

A revenue mix in which fit-out work was 54% of revenue and base rent 19% is normal for this stage of a build, but it means reported margins understate the economics of the finished asset and reported growth overstates the recurring nature of the revenue.

The gap between the order book and the income statement

{"title": "Applied Digital critical IT load: delivered, contracted and marketed (MW)", "url": "https://aistockvalue.com/api/v1/stockmind/report-assets/b90f210c-28b4-4406-b257-a10c5981e135/4ef11e47b40258ae/widget-4ef11e47b40258ae.html"}

Only 250 megawatts of the more than 1.6 gigawatts under signed lease was live and revenue-generating as of October 1, 2026, across two buildings and ten data halls at Polaris Forge 1 in Ellendale, North Dakota.〔source〕

Management expects about 300 megawatts of critical IT load across North Dakota by the end of calendar 2026, and more than 600 megawatts placed in service over the next twelve months against 250 megawatts in the prior twelve months.〔source〕

Related research

Keep researching

Sign in to keep tracking this company

Free readers can unlock up to 3 in-depth items.

Sign in to save it, keep asking the AI about this research, and follow later filings and updates.

Sign in or create an account

The research uses public information, structured data, and the assumptions shown on the page. It is not investment advice. Markets and companies can change after an update.